Celoxis can help the project manager budget project and tasks. During planning when resources are assigned to tasks, Celoxis computes the estimated cost for every task.
Estimated Task Cost = sum (Fixed cost + Estimated Material Cost + User Cost).The fixed cost of a task as entered by you. Please see Adding/Editing Tasks (Section 8.8).
This is the estimated material or non-labor cost for a task as entered by you. Please see Adding/Editing Tasks (Section 8.8).
Hours estimated to be spent by each resource (based on task durations and allocations) * user cost of each resource.
This estimated cost can be used as a guide while specifying task budget. The actual cost is automatically tracked against the budgeted amount to flag projects and tasks that are exceeding their budgets.
Viewing Estimated Cost.
Select a Project.
From the sub menu bar click →
The estimated cost of the task.
The budget of the task
Read Project Cost (Section 7.13.1) for more information.
Specifying Task and Project Budget. Task and project budget can be entered on the edit task and edit project screen.