2.2. Company Holidays

Table of Contents

2.2.1. Adding Holidays
2.2.2. Deleting Holidays

Celoxis schedules tasks around company holidays. For example, assuming that 25th December is a holiday for Christmas, a task scheduled to start on 24th December of duration 2 days will finish on the 26th and not on 25th. Company holidays along with the working hours allows Celoxis to calculate realistic task schedules. Each year you must enter the holidays for that year.