7.2.1. Assigned to me

What is it?

These are the processes where you are the owner for the current state. If timeout policy is applied on the process, the system will indicate the time in which you are expected to complete the current activity. Note that the "Due Date" field indicates when the entire process is to be completed. If you do not complete the activity on time, and if timeout policy is defined, the manager for the current state is notified and the process is marked "Delayed".